Gabon Repeat Order: 1440PCS uPVC Well Casing Pipes in 71 Days
Delivering 720 uPVC Well Casing and Screen Pipes to a Drilling Company in Gabon
In short: In September 2026, a drilling company in Gabon placed a repeat order with us for 720 uPVC well casing and slotted screen pipes (125 mm OD, 6.5 mm wall, 2.9 m each) for water well drilling at 80–100 m depth. Production took 28 days, the goods left FOB in a single 40HQ container on 15 October, and the client signed for them on 12 November. The hardest part of the job was not shipping. With a limited project budget, the client asked to replace virgin raw material with recycled material. We reviewed the project with them and recommended keeping the material and standard used in the first order.
Project at a glance
|
Item |
Detail |
|
Location |
Gabon |
|
Client |
Drilling company (repeat customer) |
|
Application |
Water well drilling, 80–100 m depth |
|
Products |
|
|
Specification |
125 mm OD, 6.5 mm wall thickness, 2.9 m per piece |
|
Quantity |
1440 pieces (about 4,176 m in total) |
|
Raw material |
100% virgin material |
|
Trade term |
CIF |
|
Shipping |
1 × 40HQ container |
|
Status |
Delivered and signed for on 12 November 2026 |
The hardest part: a budget request on raw material
The client had already received a first order from us and came back with a second one. This time the project funds were tight, and the client's idea for saving money was to use recycled material instead of virgin raw material.
It is a fair question for a buyer to ask. But well casing is installed in the borehole once and has to stay there, so a cheaper pipe that fails later costs far more than the material it saved.
Instead of simply quoting a lower price, we started from what the client was trying to achieve. We went through the target project, the drilling conditions and the drilling equipment together with the client. Based on that analysis, we recommended keeping the raw material and standard of the first order. The pipes were produced from 100% virgin material.
If you are comparing casing options for a deep well, our guides on choosing the right slot size for screen pipe and on Series 8 vs Schedule 80 casing cover the specification side in more detail.
Quality control

Quality checks on this order covered:
- Raw material: incoming inspection, with 100% new material used.
- Production: in-process dimension checks on the line.
- Finished pipe: sampling inspection, pressure testing and drop-weight impact testing. In the drop-weight impact test, the pipes showed no breakage.
- Pre-shipment: inspection on 2 October, before shipment on 15 October.
The test report and material certificate were shipped with the goods, so the client's team had the results in hand on arrival.
Timeline: 71 days from order to signing
|
Date |
Milestone |
|
2 September |
Order placed |
|
28 days |
Production, from scheduling to completion |
|
2 October |
Pre-shipment inspection |
|
15 October |
Shipped FOB, 43 days after the order |
|
3 November |
Arrived at the destination port, 19 days after departure |
|
12 November |
Signed for by the client, 9 days after arrival |
Loading: 1440 pipes in one 40HQ
Each pipe is 2.9 m long. The pipes were loaded loose, without bundling, into a single 40HQ container: 1440 pieces in four rows, with the container loaded to full capacity. That is about 4176 m of casing and screen pipe in one box.
Documents and customs clearance
The shipment went out with the full document set: commercial invoice, packing list, bill of lading, certificate of origin, COC or ECTN, test report and material certificate. The client cleared customs smoothly.
Installation support
Our technical engineer gave the client remote guidance on the key points of installation, so the crew had support on site without waiting for a visit.
Client feedback and what comes next
The client told us they were very satisfied. Their feedback singled out our sales manager, Juan, as responsible and focused on the client's interests throughout the order. A further repeat order is expected in December.
For wells that also need riser pipe for submersible pumps, see our uPVC high-pressure submersible water pump pipe. For the wider scope of what we supply to drilling contractors, visit our drilling engineering solutions, or read what PVC well casing pipe is and how it is used.
FAQ
What was shipped to Gabon in this project?
720 uPVC well casing and slotted screen pipes, 125 mm OD, 6.5 mm wall, 2.9 m each, for water well drilling at 80–100 m depth.
How long did the order take?
Production took 28 days from scheduling. The order was placed on 2 September, shipped on 15 October and signed for on 12 November, 71 days in total.
Was recycled material used?
No. The client first asked about recycled material to reduce cost. After reviewing the project and drilling conditions, we recommended the same raw material and standard as the first order, and the pipes were made from 100% virgin material.
How many pipes fit in one 40HQ container?
In this project, 720 pieces of 2.9 m pipe were loaded in four rows in one 40HQ container.