FOB, CFR, CIF or DAP for a Pipe Order? How First-Time Importers Choose
Most first-time pipe importers lose money on the trade term, not on the pipe price. The safe default is FOB Qingdao: you see the freight, you keep control, and you hold exactly the same risk position as CIF. Take CIF only if you cannot book a container yourself, and DAP only where we can deliver to your site. Everything below follows Incoterms 2020 and is general guidance, not legal advice.
• The term moves work and risk, not price: FOB, CFR and CIF land within cents of each other per metre.
• Under CIF, risk passes to you on board at Qingdao, not when the cargo reaches your port.
• Destination port charges, import clearance, duty and unloading stay with you under every term we quote.
What Changes Between FOB, CFR, CIF and DAP
All four terms start the same way. We make your HDPE pipe or PVC pipe to the agreed grade, mark and pack it, clear export customs at Qingdao and load it on board. What changes after that is who books the container, who insures, and who still carries the risk when the pipe leaves the quay.
• FOB Qingdao: you book and pay the ocean freight, and you insure from the moment the pipe is on board.
• CFR Manila: we book and pay the freight. CFR carries no insurance obligation at all, so the cover is still yours to arrange.
• CIF Manila: we book, pay the freight and insure at ICC(A) for 110% of invoice value. Risk still passes on board at Qingdao.
• DAP, selected Southeast Asian markets: we carry the pipe to the place you name. You clear import, pay duty and unload.
EXW is available on request, but it hands you export clearance as well as the freight; on pipe it rarely pays.
Who Pays for What: The 4 x 6 Table
Read the table as who does the work, not who owns the cargo. Seller is BSX Pipe; buyer is you. These six lines cover almost every argument we have had with a first-time buyer.
|
Item |
FOB |
CFR |
CIF |
DAP* |
|
Export clearance |
Seller |
Seller |
Seller |
Seller |
|
Ocean freight |
Buyer |
Seller |
Seller |
Seller |
|
Insurance |
Buyer |
Buyer |
Seller |
Seller |
|
Import clearance, duty |
Buyer |
Buyer |
Buyer |
Buyer |
|
Port charges at destination |
Buyer |
Buyer |
Buyer |
Seller |
|
Delivery to site |
Buyer |
Buyer |
Buyer |
Seller |
* DAP covers selected Southeast Asian markets only. The buyer clears import and unloads. Risk stays with the seller until the named place, which is why the seller insures.
What One 40HQ Actually Costs per Metre
One 40HQ of nested UPVC well casing: 1,251 pieces at 5.8 m, which is 7,256 m of pipe. The Qingdao to Manila ocean freight is USD 9,858 per 40HQ, or USD 1.36 per metre. Insurance at ICC(A) and 110% of invoice adds about 0.01 per metre on a 3.00 per metre pipe. On those figures:
|
Term |
Freight /m |
Insurance /m |
Landed /m |
|
FOB Qingdao |
1.36 |
0.01 |
4.37 |
|
CFR Manila |
in price |
0.01 |
4.37 |
|
CIF Manila |
in price |
in price |
4.37 |
|
DAP* |
in price |
in price |
4.49 |
Example only, built on one Qingdao to Manila shipment in November 2026. Replace the freight and the unit price with your own quote before these numbers go into a budget.
FOB, CFR and CIF land within cents of each other. When a CIF price sits far above FOB, the gap is freight carrying margin: ask for the freight line on its own and compare again.
Why Pipe Is Not Like Other Cargo
Plastic pipe is limited by volume, not by weight. A 40 ft container takes pipe in 2.95, 3.95 or 5.9 m lengths, so the joint length decides the container, the loading method and how many fusion joints your crew faces on site; our coil and straight length guide works through that trade-off. Length also drives damage: cut ends, crushed bells and ovalised sections happen in handling, and handling is exactly what the cheapest cargo cover leaves out.
The CIF Trap First-Time Buyers Fall Into
A CIF price carries two separate things: who pays, and who carries the risk. We pay the freight and the insurance, but risk passes to you the moment the pipe is on board at Qingdao. If the container reaches Manila with crushed ends, that is a claim against the insurer, not a discount from us, and the claim is yours to file. It is also why we insure ICC(A) rather than the ICC(C) minimum that CIF requires: ICC(C) covers few perils and does not cover handling damage, and handling is where pipe breaks.
Which Term for Your First Order
• No forwarder of your own: take CIF, and ask for the freight line before you compare totals.
• Own broker and a freight account: take FOB, so you keep the booking and see the real rate.
• Clearing arranged, site delivery not: take DAP, if we cover your market.
• Paying by letter of credit: FOB or CFR keeps the freight out of the credit value.
• A tender or utility project with a fixed specification: fix the term in the contract first, using our specification clause guide.
Can BSX Quote DAP or DDP?
DAP: yes, in selected Southeast Asian markets, delivered to the place you name. DDP: no. DDP makes the seller the importer of record, responsible for destination clearance and duty. We do not clear import at destination, so any DDP figure from us would rest on a local agent we do not control. If you need duty paid at your door, we will say so plainly rather than quote a number we cannot hold.
FOB vs CIF FAQ
Is FOB cheaper than CIF?
No. Both land within cents per metre; CIF simply hides the freight inside the price, so compare the freight line rather than the total.
Who pays insurance under CIF?
The seller does, at ICC(A) and 110% of invoice value, and the premium is already inside the CIF price. Ask for the certificate if your bank needs the cover confirmed.
Does CIF include unloading at Manila?
No. Destination port charges, import clearance, duty and unloading are yours under CIF, as they are under FOB and CFR.
Can you ship pipe DAP to my site?
Only in the Southeast Asian markets we cover. You still clear import, pay duty and unload; DAP is not DDP.
Which Incoterms version applies?
All four terms here are Incoterms 2020. If your contract still cites the 2010 edition, re-check the delivery and risk wording before you sign.
Send your destination port, pipe specification and quantity, and we will quote FOB, CIF and DAP side by side with the freight shown as its own line. See our solutions, or send the details to our team.
Table of Contents
- FOB, CFR, CIF or DAP for a Pipe Order? How First-Time Importers Choose
- What Changes Between FOB, CFR, CIF and DAP
- Who Pays for What: The 4 x 6 Table
- What One 40HQ Actually Costs per Metre
- Why Pipe Is Not Like Other Cargo
- The CIF Trap First-Time Buyers Fall Into
- Which Term for Your First Order
- Can BSX Quote DAP or DDP?
- FOB vs CIF FAQ